Phase 2 works will start the week commencing 22nd August.
The Project Supervisor for the Construction Stage (PSCS) is Suir Engineering. They will commence enabling works with the formation of access roads and the establishment of offsite compounds in advance of mechanical installation works, which will commence in October.
Access to and from the site will be via a one-way system. Delivery vehicles will leave M3 at Junction 5 (Dunboyne) and travel along the R157 before turning right onto the R156. From here the vehicles will turn onto the L6222 where they will travel approximately 0.5km to site. Both site entrances will be a left-hand turn from the L6222.
All traffic movements will be carried out between the hours of 08.00 to 18.00 Monday to Friday and 08.00 to 13.00 Saturdays.