South Meath solar project south site construction
South site - June 2023
South Meath solar project north site construction
North site - June 2023
  • 99% complete on module installation
  • 100% complete on structure install
  • 90% complete on cabling / wiring works
  • Ongoing works June / July – Fencing , road reinstatement , agricultural landscaping works
  • Energisation planned for mid-July

 

Resources have reduced on site, with significantly less traffic now using local road.