SOUTH MEATH    Solar Project

SOUTH MEATH    Solar Project

Project Update – September

As we draw closer to the end of the construction phase, a few points to note:

  • The substation was energised on the 30th August
  • Dispatch has commenced successfully, with the first quarter of the site now providing power to the grid, this will be ongoing for the next few weeks until all of the site is fully producing power
  • Reinstatement works are ongoing: fencing and gates being completed, and site signage will be erected in the next few weeks and then a full recapping layer on all site roads will be completed
  • All construction activity will be completed by approx. the end of October / beginning of November
View near solar panel row on sunny day
Ariel view of South Meath solar project on sunny day