- 99% complete on module installation
- 100% complete on structure install
- 90% complete on cabling / wiring works
- Ongoing works June / July – Fencing , road reinstatement , agricultural landscaping works
- Energisation planned for mid-July
Resources have reduced on site, with significantly less traffic now using local road.