- All construction works on schedule
- 100% Complete on all ramming works
- 100% Complete on all structure install
- Modules 75% complete
- All Trenching Works complete
- Cabling works on structure over 90% complete
- Module Install to be completed by Mid-June , this will result in a decrease in traffic to and from site
- All Heavy deliveries completed on site
- Road Reinstatement works to commence on site roads mid /end July
- Site Energisation period due to commence Mid-July and run until September