Project Update – June 2023

Blue info icon

South site – June 2023 North site – June 2023 99% complete on module installation 100% complete on structure install 90% complete on cabling / wiring works Ongoing works June / July – Fencing , road reinstatement , agricultural landscaping works Energisation planned for mid-July   Resources have reduced on site, with significantly less traffic […]

ALERT TO RESIDENTS

Blue info icon

It has come to our attention here at South Meath Solar Farm through a local resident that a person is calling to residents in the area offering tarmacadam jobs from left over tar after reinstatement works that hey are claiming they are carrying out. This is not associated with the Solar Farm, we are NOT […]

Project Works Update

Blue info icon

Estimated completion of piling works:  Continuing works – Ramming / Piling will continue, commencing after 8am daily, Monday to Saturday. It is envisaged that these works will be completed by end of April 2023    General Housekeeping on Roads  Road sweeping & cleaning is ongoing and being monitored daily by the site team  All material […]

Commencement of mechanical works

Blue info icon

As our project progresses, I wish to inform you, the local residents, that we will be commencing the installation of the solar panel support structures the first week of November. This phase of works will be carried out over the next number of months, with completion expected in early Q2 2023. All works will be […]

Project Flyer Delivered

Blue info icon

Our Community Liaison Team recently visited the area and as well as speaking with the local community directly, presented this Community Update brochure. Click on the image to view or download.

Road works

Blue info icon

Phase 2 works will start the week commencing 22nd August. The Project Supervisor for the Construction Stage (PSCS) is Suir Engineering. They will commence enabling works with the formation of access roads and the establishment of offsite compounds in advance of mechanical installation works, which will commence in October. Access to and from the site […]